Scope the OVH move: Migrate OVH to Hetzner. Arrange a consultation.
An OVH to Hetzner move starts by identifying what is moving: a Linux application, several public cloud instances, a dedicated server or an environment with private networks and separate databases. This guide structures the process for Linux applications you administer. It is not a universal image import or an account of a customer project.
Sources as of October 2026. The checklists are our planning recommendations, the commands adaptable examples.
Contents
- Record the estate and migration boundary
- Plan vRack and the destination network separately
- Prepare the destination before copying data
- Transfer files and databases separately
- Define cutover and the return path
- Review costs and acceptance
- Our approach at WZ-IT
- Further guides
Record the estate and migration boundary
Our recommendation: keep a per-application list of services, data sources, connections, credentials and owners. A server list alone describes neither data flows nor acceptance.
| Estate | Information to record | Destination check |
|---|---|---|
| Public cloud or dedicated server | OS, architecture, services, persistent paths | Suitable runtime and capacity |
| Database | Engine, version, extensions, roles, backup method | Restoration and business queries |
| vRack and public access | Networks, routes, permitted connections, DNS, certificates | Access through approved paths only |
| Files and object storage | Writing applications, metadata, retention | Readability, permissions and reconciliation |
| Operations | Backup, monitoring, updates, owners | Assigned responsibilities and restart procedure |
Also define what will remain at OVH. A partially relocated system needs documented connections between both environments. The decision should allow an application to remain when replacement functionality is unresolved.
Plan vRack and the destination network separately
vRack connects OVHcloud services over a private network. This does not make its network configuration transferable to another provider. At Hetzner, a Cloud Network can connect dedicated servers through vSwitch coupling; the documentation specifies a limit of one vSwitch per Network.
Our migration conclusion: redraw the required connections rather than merely copying old VLAN names. Record source, destination, port, name resolution and approval per connection. Check for overlapping address ranges and plan access during parallel operations separately. A database must not become unintentionally public during the move.
We recommend a checkpoint for every change: the application reaches its database, administration reaches the destination and unapproved access is denied. These are acceptance criteria, not test results claimed here.
Prepare the destination before copying data
For a bounded application stack, we recommend a fresh destination installation. This avoids turning unreviewed source configurations into the destination architecture. Define OS, runtime, packages, service accounts, mountpoints and startup order explicitly.
Hetzner's data migration guide covers backing up and copying data and distinguishes this from transferring whole partitions. This article likewise covers application and data transfer. A full system image requires separate checks of bootability, drivers, filesystems and networking.
Before transfer, establish destination access, storage reserve and a recovery path. Transfer accounts and secrets selectively. Overwriting destination /etc or /boot wholesale is not part of our procedure.
Transfer files and databases separately
For ordinary application files, rsync over SSH is an option. In the rsync manual, --dry-run means a trial run; -a alone includes neither hardlinks nor ACLs or extended attributes. A trailing slash on the source path denotes its contents.
rsync -av --dry-run -e ssh /srv/app/uploads/ migration@TARGET_IP:/srv/app/uploads/
Replace TARGET_IP, account and paths. Removing --dry-run copies only the named path, not a whole machine. We recommend checking the destination path, file list and permissions first. If the application needs ACLs, extended attributes or particular owners, explicitly select the necessary options and permissions. Deletion reconciliation is a separate decision.
Databases need a separate transfer method. For PostgreSQL, pg_dump produces a consistent dump of a database; this does not capture global role definitions. For other engines, choose the relevant vendor procedure. Including a running database's data directory in file synchronisation is not evidence of consistency.
Our recommended sequence: initial file transfer, database restoration rehearsal, application checks, then an agreed write freeze for the final dataset. Include background jobs and external imports in the freeze when they change the dataset.
Define cutover and the return path
Before switching, record which data source becomes authoritative. Define who freezes writes, confirms final reconciliation and approves the destination. A reachable web server alone does not establish business acceptance of the application.
Our checklist:
- Stop writing web requests, jobs and imports according to the runbook.
- Transfer final files and database state and resolve discrepancies.
- Check the destination application using the intended hostname.
- Switch DNS, external allowlists and integrations according to plan.
- Accept login, permissions, upload and a business write operation.
- Decommission the source only after approval and resolving retention.
The return path must account for new destination data. Specify how it will be handled after an abort and when the source may write again. This decision belongs in the runbook; a generic reference to DNS does not replace it.
Review costs and acceptance
For cost assessment, we recommend a common assessment period and the same service assumptions. Record source resources, destination resources, data transfer, parallel operations and subsequent operational support. Use invoices and specific quotations instead of a blanket savings rate.
Acceptance should cover data, functionality and operations: agreed datasets, permissions, external integrations, backup, monitoring and restart. Record expected and actual results. This article provides a structure, not invented measurements or a migration duration.
Our approach at WZ-IT
OVH to Hetzner migration is the matching offer for this move. If destination selection is still open, the Cloud Exit Check assesses the estate, costs and dependencies before a decision. Hetzner expertise complements the destination platform.
An application list, network overview, database type, data volume and intended operational responsibilities help scope an enquiry. Implementation and subsequent operations are defined against that estate.
Further guides
- Cloud exit strategy for SMEs
- AWS S3 to Hetzner Object Storage
- Migrate a DigitalOcean Droplet to Hetzner
- Migration overview
Plan the OVH migration: Scope the estate and destination architecture. Arrange a consultation.